Active Projects
4
across 3 properties
Total Budget
$2.8M
all active projects
Items Complete
67%
312 of 467 items
Overdue
2
past deadline
Property Project Brand Status Budget Deadline % Complete Days Left
Home2 Suites Lewisville
Home2 Suites Lewisville Guestroom Renovation Phase 2 Hilton In Progress $1,240,000 Jun 30, 2026
72%
80 days
Home2 Suites Lewisville Exterior Signage Refresh Hilton Planning $185,000 Sep 15, 2026
12%
157 days
TownePlace Suites College Station
TownePlace Suites College Station Common Area & Lobby Refresh Marriott In Progress $890,000 Mar 31, 2026
88%
11 days overdue
Hampton Inn DFW Airport
Hampton Inn DFW Airport PTAC Replacement — All Floors Hilton In Progress $520,000 Apr 5, 2026
94%
6 days overdue
Hampton Inn DFW Airport Life Safety & Code Compliance Hilton Complete $142,000 Feb 28, 2026
100%
Done
Home2 Suites Lewisville Hilton folder_open

Guestroom Renovation Phase 2

In Progress Jun 30, 2026 — 80 days remaining
Item Status Distribution
467 total items
Complete210
Installing70
Ordered47
Awarded37
Quoted33
Quoting23
Not Started28
N/A19
Category Progress
Guestrooms
82%
Building Interior
61%
Exterior
45%
Life Safety
100%
Signage
30%
Laundry / Housekeeping
55%
Total Budget
$1,240,000
Total Quoted
$1,187,400
Total Committed
$892,000
Total Actual
$743,200
Variance
+$496,800
Home2 Suites Lewisville Hilton

Guestroom Renovation Phase 2 — Items

# Description Status Install Budget Quoted Committed Actual Vendor
Guestrooms — $740,000 budget · $445,200 actual
2.01 Vinyl plank flooring — guest rooms floors 2-5 $84,000 $79,200 $79,200 $76,800 FloorCraft LLC
2.02 Case goods — dresser, desk, nightstands (126 rooms) $189,000 $182,400 $182,400 $156,200 Hospitality Furnishings Inc
2.03 Shower surrounds — acrylic panel system $67,200 $63,500 $63,500 BathPro Systems
2.04 PTAC units — 9,000 BTU (126 rooms) $126,000 $119,700 $119,700 $113,400 Amana Commercial
2.05 Vanity countertops — solid surface $50,400 $47,800 $47,800 SolidWorks Surfaces
2.06 LED lighting package — rooms + corridors $37,800 $34,200 $34,200 $32,100 LightWorks Pro
2.07 Soft goods — bedspreads, pillows, curtains $75,600
2.08 Wall vinyl — accent walls floors 2-5 $42,000 $39,600 $39,600 $38,200 WallTech Solutions
Building Interior — $210,000 budget · $131,400 actual
3.01 Corridor carpet — floors 2-5 $52,000 $48,900 $48,900 $46,200 FloorCraft LLC
3.02 Lobby furniture — lounge seating, tables, reception desk $68,000 $64,200 $64,200 $52,800 Steelcase Hospitality
3.03 Elevator cab interior refinish (2 cabs) $44,000
3.04 Breakfast area — counters, serving stations, seating $46,000
Exterior — $165,000 budget · $89,400 actual
4.01 Parking lot resurface & restripe $85,000 $82,400 $82,400 $78,600 Texas Paving Co
4.02 Pool area — deck reseal, furniture, fencing $48,000
4.03 Exterior paint — accent bands & trim $32,000 $28,800 $28,800 CertaPro DFW
Home2 Suites Lewisville Hilton

Guestroom Renovation Phase 2 — Timeline

Project Phases
Jan
Feb
Mar
Apr
May
Jun
Today
Phase 1: Life Safety & Code
check_circle Low Disruption
Phase 2a: Guestroom Construction
warning High — Floors Offline
Phase 2b: Guestroom FF&E Install
Medium
Phase 3: Exterior & Signage
Low Disruption
Recommended Renovation Windows (Based on Occupancy)
Jan–Feb
LOW DEMAND
Mar–Apr
SHOULDER
May–Aug
HIGH DEMAND
Sep–Oct
SHOULDER
Nov–Dec
MODERATE
Home2 Suites Lewisville Hilton

Guestroom Renovation Phase 2 — Budget

Budget Waterfall by Category
Guestrooms
Bldg Interior
Exterior
Life Safety
Signage
Laundry
Budget
Quoted
Committed
Actual
Category Budget Quoted Committed Actual Variance FF&E Labor
Guestrooms $740,000 $712,000 $534,000 $445,000 +$295,000 $580,000 $160,000
Building Interior $210,000 $198,000 $156,000 $131,000 +$79,000 $140,000 $70,000
Exterior $165,000 $158,000 $112,000 $89,000 +$76,000 $95,000 $70,000
Life Safety $62,000 $58,000 $58,000 $54,000 +$8,000 $32,000 $30,000
Signage $38,000 $36,000 $18,000 $12,000 +$26,000 $28,000 $10,000
Laundry / HK $25,000 $25,000 $14,000 $12,000 +$13,000 $20,000 $5,000
Total $1,240,000 $1,187,000 $892,000 $743,000 +$497,000 $895,000 $345,000
Date Amount Payee Memo
Mar 28, 2026 $12,400 FloorCraft LLC Final payment — vinyl plank floors 4
Mar 25, 2026 $8,200 Amana Commercial PTAC deposit — floor 5
Home2 Suites Lewisville Hilton

Guestroom Renovation Phase 2 — Documents

Coming in V2
folder_zip

Documents

Upload and organize PIP reports, brand letters, vendor quotes, invoices, photos, and contracts.